Planning appeals

Enforcement notice appeals

An enforcement notice has a date on which it takes effect, and your right of appeal ends the day before. Once it takes effect, failing to comply is a criminal offence. This is the one deadline in planning with no discretion in it at all.

Deadline
Before the date the notice takes effect, usually 28 days after it is served
Grounds
(a) to (g) under section 174 of the Town and Country Planning Act 1990
Effect of appealing
The notice is suspended until the appeal is decided
Fee
A deemed application fee is payable if ground (a) is pleaded
Our fee
Fixed, £500 to £1,000 for straightforward cases

What to do first

Read the date the notice takes effect, and work back from it. Everything else is secondary. If you are close to it, lodge the appeal on the grounds available and refine the case afterwards; the Planning Inspectorate allows the full statement to follow, but it cannot extend the deadline to appeal.

The seven grounds

Section 174 sets out the grounds, and you can plead more than one. They are pleaded together and argued in the alternative.

  1. Ground (a) — planning permission ought to be granted. This is a planning merits argument and it carries a deemed application, so a fee is payable. It is the ground that turns an enforcement appeal into an application for permission.
  2. Ground (b) — the matters alleged have not occurred. A factual challenge.
  3. Ground (c) — the matters do not constitute a breach of planning control. Permitted development, or not development at all.
  4. Ground (d) — the time for enforcement has expired. The immunity argument.
  5. Ground (e) — the notice was not properly served.
  6. Ground (f) — the requirements exceed what is necessary to remedy the breach. Very often the most useful ground in practice: not a fight about whether you can keep it, but about how much has to come down.
  7. Ground (g) — the compliance period is too short. Modest, but frequently granted, and it buys time.
Ground (f) and ground (g) are underused

People plead ground (a) alone, lose on the merits, and are left with the notice as drafted. Pleading (f) and (g) alongside means that even an unsuccessful merits argument can leave you with a reduced requirement and a longer period to do it in. There is no penalty for pleading grounds that fail, provided they are arguable.

The time limits changed in 2024

The Levelling Up and Regeneration Act 2023 replaced the four year rule with a single ten year rule for breaches of planning control in England, in force from 25 April 2024.

  • Breaches substantially completed before 25 April 2024: the old rules still apply. Four years for operational development and for change of use to a single dwellinghouse; ten years for other changes of use and breaches of condition.
  • Breaches on or after 25 April 2024: ten years for everything.

For a ground (d) appeal, the entire case is the evidence of when the breach occurred and that it has continued without interruption. See lawful development certificates for what that evidence looks like.

Before a notice is served

If you have had a letter from an enforcement officer rather than a formal notice, you are in a much better position than you will be in a month's time. At that stage the options include a retrospective application, a lawful development certificate if the time limits have run, or negotiated amendment. Councils generally prefer to resolve a breach than to serve a notice and defend an appeal. The time to get advice is now, not after the notice arrives.

What we do

  • Check the notice for defects in drafting and service, which are commoner than you would think
  • Identify every ground available and plead them together
  • Build the evidence for immunity where ground (d) is arguable
  • Prepare the statement of case and the merits argument under ground (a)
  • Argue down excessive requirements under ground (f) and secure a workable compliance period under ground (g)
  • Make a costs application where the Council has acted unreasonably

Questions people ask about enforcement

What happens if I ignore the notice?

Once the notice takes effect and the compliance period ends, failing to comply is a criminal offence, prosecutable in the magistrates' court with an unlimited fine on conviction. The Council can also enter the land, carry out the works itself and recover the cost from you. This is not a situation to leave alone.

Does appealing stop the clock?

Yes. Lodging a valid appeal suspends the notice until the appeal is finally determined or withdrawn. That suspension is one of the practical reasons to appeal even where the merits are difficult.

Can I just apply for retrospective permission instead?

You can, and often should, if no notice has been served yet. Once a notice is served, a retrospective application for the same matters is generally not accepted, and the route is a ground (a) appeal instead. That is the main reason acting early matters so much.

What about a breach of condition notice?

Different animal. There is no right of appeal to the Planning Inspectorate against a breach of condition notice at all. The only routes are compliance, an application under section 73 to vary the condition, or judicial review. It is one of the few places in planning where there is no appeal, and it catches people out.

Related pages

Get your fixed-fee quote

Tell us the site address and what you want to do. We will tell you what it needs, what it costs and how long it takes, in writing, before you commit.

Get a fixed-fee quote

Send the site address and a short description. You will have a reply within one working day, usually the same day.

We reply by email within one working day. Your details are used to prepare your quote and for nothing else. Or call 01202 767111.

Thanks, your details are with us.

You will have a reply within one working day. If your case is urgent, for example an appeal deadline, call 01202 767111.