Biodiversity net gain, for small sites

BNG requires most development in England to leave biodiversity measurably better than it found it. For small sites the rules changed on 6 August 2026, and a good deal of the advice still circulating online describes a system that no longer exists.

The requirement
A minimum 10% gain in biodiversity value, secured for 30 years
Measured with
The statutory biodiversity metric, from a baseline habitat survey
Main threshold
Sites over 0.2 hectares within the red line, from 6 August 2026
Householder work
Exempt
Last reviewed
September 2026

What it is

Biodiversity net gain became a condition of most planning permissions in England for major development in February 2024 and for small sites in April 2024. The requirement is a 10% improvement in biodiversity value, measured with the statutory biodiversity metric against a baseline survey of the site as it is now, and secured for at least thirty years.

The gain is delivered in a hierarchy: on site first, then off site through units purchased from a habitat bank, and only as a last resort through statutory biodiversity credits bought from the government, which are deliberately priced to be unattractive.

What changed on 6 August 2026

Following the 2025 consultation on implementation for minor, medium and brownfield development, the government amended the regime. The two changes that matter most to small sites:

  • A site area threshold. Development where the site area within the red line boundary is 0.2 hectares or less is exempt. This replaced the previous approach based on unit and floorspace thresholds, and it takes a large number of small infill and conversion schemes out of the regime entirely.
  • The self-build and custom build exemption was withdrawn for applications made on or after 6 August 2026. Applications submitted before that date keep it.

Because the position depends on your application date, transitional arrangements matter. An application submitted in July 2026 and a materially identical one submitted in September 2026 can be in different regimes.

Measure the red line, not the built area

The 0.2 hectare threshold is the site area within the red line boundary on your location plan, not the footprint of the building. A modest house on a generous plot can be over the threshold, and how the red line is drawn is a decision with real consequences. It has to be defensible, but it does not have to be generous.

The other exemptions

  • Householder development. Extensions, conservatories, loft conversions and the like at an existing house are exempt.
  • The de minimis exemption. Development affecting less than 25 square metres of on-site habitat, or less than five metres of linear habitat such as hedgerow. It does not apply where priority habitat is affected.
  • Applications made before 2 April 2024 for small sites, and before 12 February 2024 for major development.
  • Various other categories including certain permitted development, urgent Crown development and some highways work.

What it means in practice on a small site

  1. A baseline habitat survey by a competent ecologist, following UK Habitat Classification, before you submit. Habitat condition assessment is seasonal, which is the constraint that most affects programme.
  2. A metric calculation showing the pre-development baseline and the post-development value, demonstrating at least 10% gain.
  3. A biodiversity gain plan, submitted after permission is granted and approved by the Council before development may begin. This is the step people forget: BNG is secured by a pre-commencement condition, so an unapproved gain plan stops the job.
  4. Securing the gain for 30 years, through a section 106 agreement or a conservation covenant where habitat is created or enhanced.

Where small schemes get caught

  • Removing a hedgerow. Hedgerows are scored separately and are expensive to replace in metric terms. Retaining one is almost always cheaper than losing it.
  • Building over the whole plot, leaving nowhere to deliver on-site gain and forcing an off-site purchase.
  • Assuming a garden lawn is low value. Mown amenity grassland scores low, which helps; species-rich grassland does not, which does not.
  • Leaving the survey until after refusal, then finding the only survey window has passed.
  • Treating the gain plan as paperwork and discovering it is a pre-commencement condition.

How we help

We are planning consultants, not ecologists, and we do not pretend otherwise. What we do is tell you at the outset whether BNG applies to your site at all, which for a good number of small schemes it now does not; commission and co-ordinate the ecologist if it does; make sure the metric and the gain plan arrive at the right points in the process; and negotiate the condition wording so the gain plan does not become an unnecessary pre-commencement obstacle.

Questions people ask about BNG

Does BNG apply to my extension?

No. Householder development is exempt, so extensions, loft conversions and conservatories at an existing dwelling are outside the regime.

My site is under 0.2 hectares. Is that the end of it?

For BNG, from 6 August 2026, generally yes. But the exemption is from biodiversity net gain only. Protected species obligations under the Habitats Regulations and the Wildlife and Countryside Act are entirely separate and still apply. Bats in a roof are a bat problem, not a BNG problem.

How much do off-site units cost?

It varies enormously by habitat type and region, and the market has moved a great deal since 2024. Statutory credits from the government are priced deliberately high to push delivery on site or through the market. Any figure quoted in a guide will be out of date; get a current quote from a habitat bank for your area.

Can I do the metric myself?

The metric is publicly available and you are not prohibited from using it, but the baseline habitat survey underpinning it needs a competent ecologist, and Councils scrutinise self-completed metrics closely. On a site where the numbers are tight, a professional survey is cheaper than a refusal.

Related pages

Get your fixed-fee quote

Tell us the site address and what you want to do. We will tell you what it needs, what it costs and how long it takes, in writing, before you commit.

Get a fixed-fee quote

Send the site address and a short description. You will have a reply within one working day, usually the same day.

We reply by email within one working day. Your details are used to prepare your quote and for nothing else. Or call 01202 767111.

Thanks, your details are with us.

You will have a reply within one working day. If your case is urgent, for example an appeal deadline, call 01202 767111.